Monitoring Well Installation for Hydrostratigraphic Investigation at Chain of Lakes (Proj. #208-11)
Parkside Buildings Roof Re-cover (Proj. #205-10)
-
The Board on 7-21-10 authorized the general manager to execute a contract with Foam Experts Roofing, Inc., which submitted the lowest responsive and responsible bid at a bid amount of $63,500.
Patterson Pass Water Treatment Plant Clarifier Rehabilitation Project (Proj. #201-10)
-
The Board on 2/17/10 authorized the general manager to execute a contract with D.W. Nicholson Corp., which submitted the lowest responsive and responsible bid at a bid amount of $1,015,720.
Del Valle Water Treatment Plant -- Procurement of Filter Valves
Provide, Operate & Maintain Centrifuge Equipment System (Proj. #199-09)
-
The Board on 11/18/09 authorized the general manager to execute a contract with Karl Needham Enterprises, which submitted the lowest, responsive, responsible bid, in an amount not to exceed $1.98 million plus a 10 percent contingency.
Del Valle Water Treatment Plant Electrical Power System Upgrade Project (Proj. #193-09)
- The Board on 10/21/09 authorized the general manager to execute a contract with DM Jepsen Electric, which submitted the lowest responsive, responsible bid of six received, in amount of $416,798.
Large Landscape Audit Support Services
Electrical Services for Water Supply Facilities Project
- The Board on 6/17/09 authorized the General Manager to execute a contract with Harris Electric, the lowest responsive responsible bidder, in an amount not to exceed $176,890.50.
Excavating & Hauling Services for Water Supply Facilities Project
- The Board on 6/17/09 authorized the General Manager to execute a contract with California Landscape Dimensions, the lowest responsive responsible bidder, for the amount not to exceed $253,921; and to execute change orders up to 10 percent of the contract amount if needed.
Maintenance & Emergency Work for Water Supply Facilities Project
- The Board on 5/20/09 awarded the contract too the lowest responsive responsible bidder, Redgwick Construction Co., in an amount not to exceed $436,618.
Emergency Generator Preventative Maintenance & Repair Services
- The Board on 4/15/09 awarded the contract to the lowest responsive responsible bidder, California Generator Service, in the amount of $59,190.
Community Outreach, Water Education & Regonal/Local Agency Coordination Support Services
-
The Board on 5/20/09 meeting authorized the general manager to negotiate and execute an as-needed-professional services contract with Morrison & Associates, in an amount not to exceed $184,000, including a $4,000 contingency.
Publications & Website Support Services
- The Zone 7 Board on 5/20/09 authorized the general manager to negotiate and execute an as-needed professional services contract with Davis & Associates Communications, in an amount not to exceed $85,000, including a $5,000 contingency.
HVAC Preventive Maintenance & Repair Services
- A contract was awarded to Bel Air Mechanical Inc., the lowest responsive responsible bidder, in the amount of $21,395.
Ford Vehicles
- Awards were made to two separate vendors:
- Ford F-150 XLT Supercab Truck - Albany Ford, which submitted the lowest bid of seven received, at $21,248.40
- Two Ford Escape Hybrids - Livermore Auto Group, which submitted the lowest bid of eight received (after factoring in 5 percent local preference), at $56,500
Chevrolet Vehicles
- Award was made to:
- Chevy Malibu Hybrid - F.H. Daily, which submitted the lowest bid of two received, at $24,548
- 2009 Chevrolet Silverado Truck - No Award at this time.
PPWTP & DVWTP Sodium Hypochlorite Tanks Replacement Project
- The Board on 12/17/08 awarded the contract to Preston Pipelines Inc., the lowest responsible responsive bidder, for a bid amount of $557,100.
PPWTP UF Plant Ferric Chloride Storage Expansion Project
- The Board on 11/19/08 awarded the contract to Preston Pipelines, the lowest responsive and responsible bidder, for a bid amount of $282,500.
Del Valle Water Treatment Plant 3 MG and 4.5 MG Clearwell Recoating Project
- The Board on 10/15/08 awarded the contract to Redwood Painting, the lowest responsive and responsible bidder, for a bid amount of $559,960.
Patterson Pass Water Treatment Plant Improvements 2008
- The Board on 9/17/08 awarded the contract to Pacific Infrastructure, the lowest responsive and responsible bidder, for a bid amount of $878,000.
New Monitoring Key Wells Project - Bernal and Livermore
- The Board on 8/20/08 awarded the contract to Cascade Drilling, the lowest responsive and responsible bidder, for a bid amount of $227,380.
Chain of Lakes Wells Nos. 1 & 2 Facilities and Sitework Project
- The Board on 8/20/08 awarded the contract to Conco West, Inc., the lowest responsive and responsible bidder, for a bid amount of $7,367,655.
El Charro Pipeline, Phase 1
- The Board on 6/18/08 awarded the contract to Marques Pipeline, Inc., the lowest responsive responsible bidder, for a bid amount of $2,195,592.
Former Camp Parks Pipeline Lining & Connections
-
The Board on 6/18/08 awarded the contract to Sanco Pipelines, Inc.,the lowest responsive responsible bidder, for a bid amount of $1,487,865.
Maintenance and Emergency Work for Water Supply Facilities
- The Board on 6/18/08 awarded the contract to GSE Construction Co., the only contractor to submit a bid for the project, for an amount not to exceed $376,000.
Excavation and Hauling Services for Water Supply Facilities
- The Board on 6/18/08 awarded the contract to Joe Shaver Backhoe Service, the lowest responsive reponsible bidder, for a bid amount of $278,247.
Electrical Services for Water Supply Facilities
- The Board on 6/18/08 awarded the contract to All Bay Electric, the lowest responsive responsible bidder, for a bid amount of 169,293.50.
Altamont Pipeline Project, Livermore Reach
- Following a competitive bidding process, the Board on 4/16/08 awarded the construction contract to Ranger Pipelines Inc. for $22.8 million. The Board also authorized support services agreements with Harris and Associates for construction management, CH2M Hill for construction engineering support, ICF Jones & Stokes for public outreach and environmental services and Consolidated Engineering Lab for materials testing and specialty inspections.
|